Key Features

  • Construction of 3.5km of rising main sewers
  • Construction of 2Nr. Pumping Stations
  • Construction of Wastewater Treatment Plant
  • Construction of 1.5km of Gravity Sewer
  • 600m Marine Outfall
Contract Value :

€6.1 Million

Contract Type :

FIDIC Gold Book

Client :

Irish Water

Start/End:

June 2016 - December 2017

Company Involvement:

The Belmullet Sewerage Scheme DBO project was awarded to Roadbridge in April 2016 Roadbridge undertook the position of Main Contractor and PSCS for the construction of the pipelines pumping stations and while EPS will be PSCS for the waste water treatment plant Ryan Hanley Consulting Engineers are the clients rep for this project

Project Description

This project, located throughout Belmullet in County Mayo comprises the following: • Construction of 3.5km rising main sewers • Construction of 1.5km of gravity sewer • Construction of 2 No. pumping stations • Construction of a Waste Water Treatment Plant with a population equivalent (PE) of 2500 • Associated services including house connections, ESB ducting • Working in an Urban / Industrial environment. • 600M marine outfall