Key Features

  • Remedial repair of 4 No. 2.3 MW Siemens Wind Turbine Generators
  • Relocation of existing unit transformers and cabling
  • Testing and Commissioning of WTG's and Transformers
  • Resin injection of all existing cracks
  • Steel reinforcement, concrete pouring and post tensioning of new bases
Contract Value :

€2 Million

Contract Type :

Fixed Price / Lump Sum

Client :

SSE Renewables

Start/End:

June 2014 - December 2014

Company Involvement:

Roadbridge performed the role of Main Contractor and PSCS for the remedial works. Roadbridge in its capacity as PSCS coordinated all works associated with the remedial works and the operational Wind Farm Site. This involved consultation and coordination with all relevant stakeholders & landowners.

Project Description

The site is located within an existing operational Wind Farm in Co. Donegal. The Works comprised the construction of the remedial repair for the existing WTG foundations of Cark Extension Wind Farm which comprises 4 No. 2.3 MW rated Siemens Wind Turbine Generators (WTGs).The remedial works consisted of resin injection of all existing cracks, steel reinforcement placement, concrete pouring and post tensioning of new bases constructed around the existing bases. The Works also required relocation of the existing unit transformers and associated extensions of underground cables and re-wiring and testing & commissioning of same.